Project Server - How to monitor Project milestone change

The following post title strike to me on TechNet forums few days back:

How to monitor and control the change in Project milestone tasks?

And here I decided to write a blog about the solution i chose some time back last year when I was involved in an EPM implementation project for one of the leading Bank in Middle East.

One of the not-OOB requirements of Project Management Office is about the monitor and control they look for over the projects based on the project milestones. The first quick thing you can propose is the Dashboard reports, where you can develop indicators based on the PMO criteria and they can reflect a bird eye view of the Project status at the milestone level. But think about the scenario where you have more than 50 big project schedules and each with over dozen of milestones, the dashboard solution would not really be welcomed if the program officer has to scroll down to all the milestones of each project to see which of the indicator is turned red due to the change in milestone cost/duration/ etc.

The solution i developed and accepted by the customer with smile was:  
  • Generate an email notification to the PMO,
  • if any project milestone task estimation varies with the baseline estimation.
  • This will intimate the PMO rite away about the change with Project name, Project Manager Name, and the exact changed milestone task within the project.
This could further compliment with the SSRS dashboard report, where then program officer can go and browse that particular project for details instead of scrolling to each and every project. Also the PMO don't have to view the reports every now and then, instead they can only access when they receive any change notification - this can also be called more productive at the PMO end.

The way I managed to do that is as follows:
  • Project manager changes the project schedule and publish the project 
  • Trap the OnPublished event 
  • Check for the change at the milestone level. For instance compare the Project milestone cost value with the Project milestone baseline Cost value.
  • If found any variation, create and send an email to the PMO or etc.
The solution however based on the baseline of the project, and also the permission to save the baseline should not be allowed to the Project manager. Because the variance can only be determined after the comparison of current and the baseline values, customizing the event also requires coding.

You need to set you IDE environment to access the Project web service methods. There is an excellent article available on MSDN about How to Create and Debug the project custom event handler, so i will not go in that detail. We will override the OnPublished event, the reason i prefer to use OnPublished is because its a post publish event triggers after completing the required publishing activities and wont effect the publishing in-case of any abnormal termination due to the exception in the custom code.




The next step you have to do is to define a Project Object, call its method ReadProject using project GUID and save the project data in a dataset.


Once the project data is saved in the dataset, you can now evaluate each milestone in the project to check for any variance in the cost values:

foreach (NotificationEventHandler.Project.ProjectDataSet.TaskRow dr in drs)
{ 
iTaskCostVar = (dr.IsTASK_COST_VARNull() ? 0 : Convert.ToInt32((dr.TASK_COST_VAR)));
.
.
.
}

If finds any difference, save the task name with all the other details required and draft an email based on that data. For instance:

_______________________________________________________________________________

sEmailStart.Append("<html><body>"); 
sEmailStart.Append("Dear Finance,<br> CC: PMO<br><br>");
sEmailStart.Append(string.Format("Project Name: {0} has been modified. Please review the Project Milestones as below:<br><br>", ds.Project[0].PROJ_NAME));
sEmailStart.Append("<table border=2 cellpadding=2 cellspacing=2 width=100%><tr><td>Name</td><td>Baseline Start</td><td>Actual Start</td><td>Baseline Finish</td><td>Actual Finish</td><td>Baseline Cost</td><td>Cost</td><td>%Complete</td></tr>");
sEmailStart.Append(string.Format("<tr><td>{0}</td><td>{1}</td><td>{2}</td><td>{3}</td><td>{4}</td><td>{5}</td><td>{6}</td><td>{7}</td></tr>", dr.TASK_NAME, sBaselineStart, sActualStart, sBaselineFinish, sBaselineFinish, sBaselineCost ,sCost, sPctComplete));
sEmailStart.Append("<br>Please review them by following the link: ");
sEmailStart.Append(configurations["ProjectServerURL"].ToString() + "/project.aspx" + "<br><br><br>");

 sEmailStart.Append("Regards, <br> EPM Team  <br><br><br> Note: This is an auto-generated email, please don't respond");
sEmailStart.Append("</body></html>");
_________________________________________________________________________________
Once done with the development , add the library in the windows assembly and register the event handler with the appropriate Project server event. Follow the MSDN article i have mentioned above for debugging and deployment, all the steps are explained in detail in that article.


Add in windows assembly


Register Project Server event handler


And based on your requirement you can send this email through the code either to the pre-defined users (you can use web.config for this) or you can read any particular user's email on the fly from DB based on some defined criteria. Now if the project manager changes the milestone cost, our code will execute when he will publish the project after the change. And like the below project schedule, the change in milestone could be detected and the email will be generated to the PMO.



Your email might look like this in the end:



This email contains all the changed milestones with the exact change details, project center link to access the project other details and the effect this change propagates to the whole project schedule. Now imagine being a part of the PMO, you receive a notification on your outlook about the change in the project milestone by one of your Project Manager, you can quickly log on to your PWA, verify the change and its impact and can take the necessary steps. Doesn't it sound simple and quick? trust me it indeed is the quickest way for PMO to monitor the change in the project :) 

As always any comments and suggestion are more than welcome.

Updated (26th Jan): The solution will work for Project Server 2007 as well as the PS 2010. Forgot to mention this earlier, adding it now after the valuable feedback of none other than Christophe Fiessinger.

Below is the complete code snippet of the solution for reference, but do note that the code attached has been written for the testing, and specific to the requirement, purposes only and attached as is. The code should be improved and revised, as per the requirements, prior to the deployment on the production server.

 ______________________________________________________________________________
public override void OnPublished(Microsoft.Office.Project.Server.Library.PSContextInfo contextInfo, Microsoft.Office.Project.Server.Events.ProjectPostPublishEventArgs e)
{

base.OnPublished(contextInfo, e);

try
{

string Task_Cost_Var = string.Empty;
string sEmailFrom = string.Empty;
string sToFinance = string.Empty;
string sToPMO = string.Empty;
string sEmailSubject = string.Empty;
string sSMTPServer = string.Empty;
string sBaselineStart = string.Empty;
string sActualStart = string.Empty;
string sBaselineFinish = string.Empty; 
string sActualFinish = string.Empty;
string sBaselineCost = string.Empty;
string sCost = string.Empty; 
string sPctComplete = string.Empty;

int iTaskCostVar;


//string sConnString = string.Empty;


StringBuilder sEmailStart = new StringBuilder();
int iSMTPPort = 0;
int iMilestoneCount = 0;

XmlTextReader reader = new XmlTextReader(@"C:\EPMConfigurations\Config.xml");
Hashtable configurations = new Hashtable();

while (reader.Read())
{

string lastKey = String.Empty;

if (reader.NodeType == XmlNodeType.Element)
{

if (reader.Name.ToLower() == "add")

{

configurations.Add(reader[0], reader[1]);

}

}

}


reader.Close();

NotificationEventHandler.Project.Project p = new NotificationEventHandler.Project.Project();

p.Url = configurations["ProjectServerURL"].ToString() + configurations["PROJECT_WEBSERVICE"].ToString();


p.Credentials = CredentialCache.DefaultCredentials;

NotificationEventHandler.Project.ProjectDataSet ds = p.ReadProject(e.ProjectGuid, NotificationEventHandler.Project.DataStoreEnum.WorkingStore);

//ds.b


NotificationEventHandler.Project.ProjectDataSet.TaskRow[] drs = (NotificationEventHandler.Project.ProjectDataSet.TaskRow[])ds.Task.Select(ds.Task.TASK_IS_MILESTONEColumn.ColumnName + " = 1");


//sEmailStart = ds.Project[0].PROJ_NAME + Environment.NewLine + Environment.NewLine + "Below are the latest Milestone Tasks Cost changes occur:" + Environment.NewLine;

sEmailStart.Append("<html><body>");

sEmailStart.Append("Dear Finance,<br> CC: PMO<br><br>");

sEmailStart.Append(string.Format("Project Name: {0} has been modified. Please review the Project Milestones as below:<br><br>", ds.Project[0].PROJ_NAME));

sEmailStart.Append("<table border=2 cellpadding=2 cellspacing=2 width=100%><tr><td>Name</td><td>Baseline Start</td><td>Actual Start</td><td>Baseline Finish</td><td>Actual Finish</td><td>Baseline Cost</td><td>Cost</td><td>%Complete</td></tr>");

//check if there are any milestones in the project,if not simply return
if (drs.Length == 0)
return;
foreach (NotificationEventHandler.Project.ProjectDataSet.TaskRow dr in drs)
{

//check if milestone cost changed, if not skip for this and check the other row

iTaskCostVar = (dr.IsTASK_COST_VARNull() ? 0 : Convert.ToInt32((dr.TASK_COST_VAR)));
if (iTaskCostVar == 0)
continue;

sBaselineStart = (dr.IsTB_STARTNull() ? "0" : (dr.TB_START).ToString());
sActualStart = (dr.IsTASK_ACT_STARTNull() ? "0" : (dr.TASK_ACT_START).ToString());
sBaselineFinish = (dr.IsTB_FINISHNull() ? "0" : (dr.TB_FINISH).ToString());
sActualFinish = (dr.IsTASK_ACT_FINISHNull() ? "0" : (dr.TASK_ACT_FINISH).ToString());
sBaselineCost = (dr.IsTB_COSTNull() ? "0" : (dr.TB_COST/100).ToString());
sCost = (dr.IsTASK_COSTNull() ? "0" : (dr.TASK_COST).ToString());
sPctComplete = (dr.IsTASK_PCT_COMPNull() ? "0" : (dr.TASK_PCT_COMP).ToString());

sEmailStart.Append(string.Format("<tr><td>{0}</td><td>{1}</td><td>{2}</td><td>{3}</td><td>{4}</td><td>{5}</td><td>{6}</td><td>{7}</td></tr>", dr.TASK_NAME, sBaselineStart, sActualStart, sBaselineFinish, sBaselineFinish, sBaselineCost ,sCost, sPctComplete));

iMilestoneCount = iMilestoneCount + 1;
}
sEmailStart.Append("</table>");

//check if there are any milestones appended in the string because of cost variance,if not just return


if (iMilestoneCount == 0)
return;

//sEmailStart = sEmailStart + Task_Cost_Var; 
sEmailStart.Append("<br>Please review them by following the link: ");
sEmailStart.Append(configurations["ProjectServerURL"].ToString() + "/project.aspx" + "<br><br><br>");
sEmailStart.Append("Regards, <br> EPM Team <br><br><br> Note: This is an auto-generated email, please don't respond");
sEmailStart.Append("</body></html>");
sEmailFrom = configurations["EmailFrom"].ToString();
sToFinance = configurations["ToFinance"].ToString();
sToPMO = configurations["ToPMO"].ToString();
sEmailSubject = configurations["EmailSubject"].ToString();
sSMTPServer = configurations["SMTPServer"].ToString();
iSMTPPort = Convert.ToInt32(configurations["SMTPPort"].ToString());
MailMessage MilestoneEmail = new MailMessage(); //(sEmailFrom, sEmailTo,);
MailAddress MailFrom = new MailAddress(sEmailFrom);
MilestoneEmail.From = MailFrom;
MilestoneEmail.To.Add(sToFinance);
MilestoneEmail.CC.Add(sToPMO);


AlternateView htmlView = AlternateView.CreateAlternateViewFromString(sEmailStart.ToString(), null, "text/html");
MilestoneEmail.AlternateViews.Add(htmlView);
MilestoneEmail.IsBodyHtml = true;
MilestoneEmail.Subject = sEmailSubject;
//MilestoneEmail.Body = sEmailStart;
SmtpClient smtpClient = new SmtpClient(sSMTPServer, iSMTPPort);
smtpClient.Send(MilestoneEmail);

}


catch (Exception err)
{

string errorMessage = "Code crashed OnPublished Method" + err.Message + " " + err.Source + err.StackTrace;
el = new ErrorLog();
el.CreateFile();
el.WriteToFile(errorMessage);

}
______________________________________________________________________________


Tuesday, January 18, 2011

Project Server 2010 SDK updated

Folks,

Great work by Jim Corbin on Janudary 2011 update of the the Project 2010 SDK, its available online on MSDN. The new update is available online only, the download will be available within 2 months.

The SDK contains documentation, code samples, how-to articles, and programming references to help customize and integrate the Project 2010 clients and Microsoft Project Server 2010 with a wide variety of other desktop and business applications for enterprise project management.

The new udpate contains the following topics:
It also contains the new and updated description of the Project Server API references, and new code samples all based on WCF.

For more details, browse the Jim's blog and for the complete reference check the SDK on MSDN online. Also i am quite excited about the beta release of the feature pack for integration between Project Server 2010 and TSF 2010. I would definetly share my experience once i will try the integration, the release was indeed worth waiting.

Monday, January 10, 2011

Nintex Workflows for Project Server 2010

Without any doubt the one of the most exciting feature of Project Server 2010, at least to me,  is the Demand Management Process. The Demand Management let you automate your Project life cycle with great control and visibility, and let you capture your project rite from its inception stage till the closure stage. In Project Server, server settings the new section has been added 'workflow and project detail pages' that consist of EPT, Phases, Stages and Project Detail Pages. Using all of these options together can give you a great leverage of creating a Project workflow.And the more great deal about this is that you can automate more than one Project life cycle process, to fulfill the demand of different processes within one organization, by creating different workflows and associating them with the different EPT. And further filter them on the basis of Departments (another awesome feature of the Project Server 2010, will discuss in my future post) to be available only for the target audience.

Now this is not the only reason i am writing this post, because there is already a lot of excellent material available related to Demand Management capabilities. The feature has also led this misconception among the users that they are going to get the workflows also as an OOB features of Project Server 2010. And that they will be able to use it straight away by simply configuring the workflow section available within the server settings of the Projec Server. Or the workflow is something which they can download from the internet and use it, thanks to the dynamic workflow available in the solution starter kit :). The conclusion is based on my personal experience and often i have to work really hard in clearing this wrong concept from the customers head.

And this, developing a workflow, requires effort and expertise. As they say that not all the ease can come without small amount of pain :). The fact of the matter is that  Project Server 2010 workflow cannot be built using Sharepoint designer and thus leaves the customer with only two options:
  1. Leverage the Dynamic Workflow Solution Starter, a Microsoft released tool that enables simple approval type linear workflows to be built from within a web page without any code; or
  2. Get a .net developer to use Visual Studio 2010 to design, develop and test a  workflow that meets all the organizational requirements.
However, now there is a third option available i.e Nintex Workflows for Project Server 2010, an extension of the popular Nintex Workflow 2010. The new NWFPS 2010 brings a simplified drag and drop interface for building workflows and integration into the Project Server workflow components to users via the web browser. The tool is looking promising. and the deployment and its integration with the Project Server is seamless.




Unfortunately i was not getting much time to explore its capabilities, but look for my next blog where i will write in more detail about the usability and capability to create a workflow using NWFPS 2010.

Saturday, January 8, 2011

Project Server 2010 - Team Member Group Permissions Bug

In my blog, i would like to highlight one of the issue been fixed after applying the December CU of Project Server 2010. Few weeks back i come across this issue while i was trying accessing Projects as Team Member group user. Initially i thought it was me who forgot to check an appropriate category permission but after confirming few times all the settings, my doubt became concrete when i browse through a techNet site - where more than a few users have registered a similar incident as an Issue.

To make my self more meaningful, below is the scenario:

Scenario:
  • Resource is a member of Team Member group.
  • Resource is only allowed to view the Project plan
  • Resource is not allowed to edit any Project custom field information
  • Resource is not allowed to edit Project Schedule
Following is the screen shot of the Team member group permission following the above scenario:


Result:

When user of the above mentioned group try to access the project detail from the Project Center, the user will end up with the following error.
When access project, Error.
First Solution:
For the sake of work around, if you only allow user to Edit Project Custom fields (which ideally shouldn't be allowed), it will work.




The user is now able to edit the Project summary fields, but not able to change the Project schedule.

Second Solution:
If you deny the Edit Project Summary fields and allow user to Save project to project server and publish project (ideally this shouldn't be allowed to team members) it will work: The user will not be able to edit the Project custom fields, but enable to update the Project Schedule :)


The fact of the matter is, both the above solutions are not acceptable for customers. It does not make sense that the user of the Team Member group can update Project custom field or Project Schedule or both. I have also found a comment of one of the senior moderator at techNet, and he wasnt agreed of calling it an issue and rather explained it as design behavior of new Project Server 2010. But on a contrary, i stick to my opinion of calling it a Issue, as to me no design is good if its unable to fulfill customers basic requirement.

Although the Microsoft has released a hot fix ( http://support.microsoft.com/kb/2459112/) to fix the above issue. The more good news is that MS has also released December CU for Project Server 2010 (http://support.microsoft.com/kb/2459258/) which contains this fix along with the other fixes. Applying this CU will enable Team member users to access the Project detail only by allowing them to Open Project group permission.


Friday, January 7, 2011

Project Server 2010 - December CU released

This is to echo Brian Smith announcement of the release of the latest Project Server 2010 Cumilative Update.  Cumulative update packages for Microsoft Project Server 2010 contain hotfixes for the Project Server 2010 issues that were fixed since the release of Project Server 2010.

It fixes few of the really required issues, such as team member permission to view projects and setting the project owner of the project. The more detail of the CU can be viewed on the following link:

In order to find out the current version of CU or Hofix of your Project Server 2010, follow the Brian Smith article for details: http://blogs.msdn.com/b/brismith/archive/2010/09/23/how-to-tell-which-cumulative-update-hotfix-or-service-pack-version-of-project-server-2010-and-project-2010-you-are-running.aspx.

Look for my upcoming blog where i am going to write in detail about 2 of the issues fixed after applying this CU. Please also note that, do not apply this CU in your production environment without testing.

Thursday, December 30, 2010

Project Server 2010 - Configure Excel Data Connections

I have seen quite frequent postings related to the excel services configuration, but the good thing is that Microsoft is supporting the Project Server 2010 the way they never done it before. Details postings related to every issue can be found on TechNet, MVP blogs etc. to help users.
Few days back I came across this issue for which I was unable to find any specific solution on Google. It was straight forward though, but still worth posting.


You will face this if you create a excel report using one of the cubes and try to open the report in your browser and refresh the data. There are some very useful articles in TechNet available to configure the excel services to work with Project Server data. Following the steps explained in that article will let you open the built-in reports and data connections.

But when you configure your cube to be build, the system will save the Cubes on a predefine location i.e.: within Business Intelligence -> Data Connection, a new folder will be created <server name-cube name> to save the cube. And when you use cube to create report in excel and publish to the web, the system will decline to authorize the data connection when refresh because the cube location is not defined in the Trusted Data Connection library.

The only location you define following the article is the OOB connection library. Any new data connection you create, you also have to define in the trusted data connection library to enable to refresh the data.


Following are the screen shots to explain the issue.

Fig-1 shows the error:

“The data connection path in the workbook points to a file on the local drive or is an invalid URL…..”

Fig -2: shows the folder system created to store the Cubes. You will find the difference between the URLs if you verify this location with the location you have saved in the trusted data connection library.

Fig -3: If you click on the folder, you will see all the cubes created. The modified date shows the latest Cube built date.

Fig -4: Define the path of the cube folder in the trusted connection.

Fig-1
Fig -2
Fig -3
Fig -4
Conclusion: the solution is pretty simple, for every custom data connection – you have to define the location in the trusted connection library.


Tuesday, December 21, 2010

Project Server 2010/2007 Permission Settings

Assuming yourself at client side, finalizing your PWA configurations including Group permissions and planning to sit with the client to go through the PWA home page - and just found that the end user being part of the Project Manager group can also be able to delete any item from the custom list, able to change the web part settings, able to change the PWA theme and so on.

Now this will leave you wondering that how this is possible, and you might go through your Group/Category settings agains to verify the permissions. Actually apart from Group/Category permission, you also have to customize the PWA site permission to avoid any such situation. When you provision the Project Web App site, the default PWA site permission settings grant way too much permission to a user which in most cases are not acceptable. The groups permission settings allows user to use the PWA features, few of them are such as:
  • Accessing Projects
  • Accessing Resources
  • Accessing Views
  • Administrative settings
Now as stated above, after provisioning the PWA site, Project Server creates four levels of permissions for the PWA site:
  • Web Administrators (Microsoft Office Project Server)
  • Project Managers (Microsoft Office Project Server)
  • Team Members (Microsoft Office Project Server)
  • Readers (Microsoft Office Project Server)
Do not confuse this Project Manager group here with the Project Manager groups available in server settings of your PWA. This Project Manager group include all the users:
  • who have the permission to save project OR
  • permission to publish the project on project server.
which means that if you have configured your Portfolio Manager Group/Team lead group to have any one of the above permission, they will be part of this permission level. So basically we have to customize the permission level of Project Manager Group and Team Members Groups.

To resolve the issue, we are simply going to set the permissions of the Project Managers (Microsoft Office Project Server) and Team Members (Microsoft Office Project Server) permission levels within the PWA Root site to be equal to that of the Readers (Microsoft Office Project Server) permission level. To do this:

  1. Log in to PWA as an Administrator
  2. Expand the Site Actions menu by clicking on it
  3. Click Site Settings

    4.   On the Site Settings page, under Users and Permissions, click Site Permissions



    5.   On the Permissions: Project Web Access page, click Permission Levels



You should now see the Permission Levels page. You should see thirteen Permission Levels listed — the four i have described earlier, and the standard SharePoint ones (Full Control, Design, Contribute, Read, Limited Access, View Only, Approve, Manage Hierarchy, and Restricted Read).

Click on the Project Managers (Microsoft Office Project Server) permission level, and uncheck the permission as per your requirement, such as:



  • Manage Lists
  • Overide Checkout
  • Delete items
  • Manage permissions
  • create subsites
  • Apply theme and borders
  • Manage Alerts
  • Create Groups, etc.

Click Submit, which will return you to the Permission Levels page. Now, click on the Team Members (Microsoft Office Project Server) permission level, and uncheck the not required permissions as above.

Removing these permissions prevents non-admins from altering the look, structure, or content of pages and etc. within PWA. We also prevent them from altering lists, discussion boards, and document libraries in PWA. Note that changes to these List permissions do not affect the ability to link Tasks to Workspace Items (documents, issues, deliverables, or risks); this behavior is controlled by the Create Object Links Category permission.




Friday, December 10, 2010

Project Server 2010 Version after OCT CU

Since its been a while a Project Server 2010 is released, and Cumilative updates for the product are also been released. You might come across a situation where you want to make sure if your Project Server version is the latest version or not.

Check the following locations for the Microsoft.Office.Server.dll to determine the version. If the version is 14.0.5128.5000 or greater, the October CU, which apparently is the latest hot fix of Project Server 2010 so far, is applied.
  • C:\Program Files\Common Files\Microsoft Shared\Web Server Extensions\14\ISAPI\Microsoft.Office.Server.dll
  • C:\Windows\assembly\GAC_MSIL\Microsoft.Office.Server\14.0.0.0__71e9bce111e9429c\Microsoft.Office.Server.dll

Saturday, December 4, 2010

Project Server 2010: October Cumulative Update now re-released!

This is just to announce that the new CU of Project Server 2010 is now re-released. See the revised article related to the CU: http://blogs.technet.com/b/projectadministration/archive/2010/10/27/microsoft-project-server-and-sharepoint-2007-and-2010-october-cu-2010-are-live.aspx.

So all the Project Server consultants/administrators, visit the following website to read the details and download the Update:
http://technet.microsoft.com/en-us/projectserver/gg176680.aspx

Ref: http://blogs.msdn.com/b/brismith/archive/2010/11/18/project-server-2010-october-cumulative-update-now-re-released.aspx

Thursday, December 2, 2010

Migrating Content Data from Project Server 2007 to Project Server 2010

Recently i have migrated Project Server 2007 data to Project Server 2010. Restore and Backup of the following 4 Project Web App 2007 databases had restored all the Project data, custom fields, views and etc.
  • Project Server Archive
  • Project Server Draft
  • Project Server Published
  • Project Server Reporting
I have also had to migrate the content data from Project Web App, such as:
  • lists
  • folders
  • list items (including files)
The migration of PWA artifacts is something that’s perhaps more complex than it should be. And in almost all the cases the requirement is to migrate the content without modifying the date and author details ( the other case is quite easy that moving the content from one site to another without being worried about the date/author details). I discovered that there are a few ways to accomplish this task.  You can migrate a single list from Project Server 2007 to Project Server 2010 using one of the two methods:
  1. Migrate a single list from Project Server 2007 to 2010 using the detach PWA Content database method
  2. Migrate a single list from Project Server 2007 to 20110 using PowerShell
The limitation with the first option is that if there is any custom branding applied to your source PWA 2007 site, the migration will bring that branding to your target PWA 2010 site as well. Which in my case was not requried, so we will discuss the second option in detail. I would also like to introduce this very handy tool i have found after bit of a googling over the net, it would ease your life alot. The tool is  developed by Chris O’Brien to move the content from one farm to another, its bascially using the stsadm import/export commands to do the job, but its little tricky when its come to moving the data from Project Server 2007 to Project Server 2010. if its the same version of Project server, it would work straight away.
The tool provides a wizard-like approach to deploying content between PWA sites. The selected content is exported using the Content Migration API (PRIME), giving a .cmp file (Content Migration Package) which can be copied to other servers. the tool must be installed locally on the server which hosts the site, so you have to install it on both your source and target servers respectively to import and export the job.

EXPORT CONTENT
1. Run the application as an administrator, choose Export and enter the URL of your PWA site.






2. Choose from the Export content tree view, right click on the selected content and click Export. You can also use Include Descendant option on the container objects such as Webs. I would prefer to select one list at a time, import it as .cmp file and then re-run the wizard to create a .cmp file of another list. The reason is that stsadm Import command breaks the .cmp file in more than one file if the size of the content exceeds 25MB. Even if the single selected list exceeds the maximum size limit (25MB) you have to opt for the non-compressed option (that we will discuss in next stage), because creating and importing multiple files gave me a hard time.

 
3. After selecting the list, click on Next to move to the next scree where we have to configure the settings before creating a export file. Do the following settings and click next.
  • Export method: Export all
  • Include Version: All
  • include Security: All
  • disable compression: select if your data is more than 25MB.



4. The next will create a *.cmp file for you. Re-run the wizard again if there are other date need to be exported.

IMPORT CONTENT


5. Once you will have all your *.cmp files with you, copy them on the target server. Prior to running the wizard to import the files you have to verify the version in SYSTEMDATA.XML file which resides within the *.cmp file else it will fail to import the content and the error dialog box with the following error will appear:

The import process failed with following error:
FatalError: The version of the package 12.0.10.0 is different from the current version this program supports, 14.0.0.0.
Debug:    at Microsoft.SharePoint.Deployment.SPDeploymentSchemaVersion.Validate(SPSite site)
at Microsoft.SharePoint.Deployment.SPImport.Run()
Progress: Import did not complete.


The import process save the current version of Sharepoint server during the process, and when you try to export the file into the different Sharepoint version, the process fails.  follow the steps to update the version number and then run export the file, repeat the same steps for all the *.cmp files.

5a. Change this CMP file to CAB, extract the file so that you can access SystemData.xml in the CAB file, and modify the version information there. Open the SystemData.xml file in a text editor, and change Version=”12.0.0.0″ to Version=”14.0.0.0″, and Build=”12.0.0.6514″ to Version=”14.0.4762.1000″.







5b. You will have to create a new CAB file again after making the changes above. go to the link: (http://www.larshederer.homepage.t-online.de/cabpack.htm) and download the cabpck14.zip. Unzip the file and run the cabpack.exe, browse and select the folder where you have your modified files are and run the cabpack. It will create a new *.CAB file for you which you can rename to *.CMP to run import.








6. Run the wizard, select the Import option and enter the URL of your PWA 2010 website in both the boxes.
(if you have created a non-compressed export data of your list, jump to the point 9 directly)







7. On the next screen, browse the *.cmp file, do the following settings and click Next:
  • Retain object IDs: Keep it un-checked if you want your list to be create and configured within the PWA site.
  • Include Security: All (if you dont want to modify the date/author details of the items)
  • Version Options: Append
  • User Info: Import all



8. The import process will execute in the next step and will open a log file for you at the end of the process. If it will be finish successfully without any errors, you can simply go to your PWA 2010 site refresh the page and will witness the changes.







9. In a case of uncompressed export, you can have a folder of files consisit of *.dat and the other configuration *.xml files.

Follow the same steps 5a and 5b to modify the version and create a *.CAB file. And then run as administrator the sharpeoint 2010 Management Shell to import the content. Run this instruction:

import -spweb -identity <PWA site URL> -path <*.CMP file path> -IncludeUserSecurity







In summary, if you have a need to just import a PWA list from an existing Sharepoint 2007 farm to a SharePoint 2010 farm, there are several ways to accomplish this task. Which method you should use will depend on the tools that you have available, and your familiarity with each of them.

Please leave your comments and queries and dont forget to rate the article,  thanks.